사람이 많이 오는 곳이라서 질문 좀 할게요

  • #410476
    도와주세요 149.***.202.78 2570
    In a Manufacturing plant there are constraint machines in Department 25.  There are 30 machines and 15 operators.  Set up is done using help from available operators to minimize time spent on changeovers. The company is on a standard cost system and standard hours are set on direct labor man-hours.  Efficiency is earned compared to these labor standards. On this particular week the following rates of earned hours were achieved:
    Monday     Tuesday     Wednesday     Thursday     Friday
     120             118              101                 125            99
    If standards are set at an expectation of 7.5 hours per day per direct labor employee, and all employees were there for the full 8 hours each day, what is the efficiency for the department?
    이거 풀수 있으신 분 있나요? 도와주세요 모르겠어요….
    • z 71.***.11.159

      숙제는 니가 해야지 이 김치년아.

    • 75.***.75.147

      봄 학기 때 관리 회계학 클래스에서 배웠던 내용 같은데 여름 지나고 보니 다 까먹었네 ㅎㅎ;;

    • ㅋㅋ 76.***.59.226

      솔직히 풀 줄 모르는 사람들만 댓글 달듯 ㅎㅎ

    • ㅍㅍ 99.***.194.10

      음,, 전공은 아니지만, 제 생각으로 계산해보면, () 안은 단위

      주당 실제기계작동량 = 563 (machine hour)
      주당 노동가능작업량 = 40(hour) x 15(man) x 7.5/8 (작업가능비율) = 562.5 (man hour)

      작업효율 = 실제기계작동량 / 노동가능작업량 … 으로 생각해 볼 수 있지 않을까요? 대충 이런식일것 같아요. 전문가께서 풀어주시길~